Completion of the first row of stone blocks. Block-laying is carried out using a band-saw to ensure precision and accuracy when creating doorways and windows.
Completion of the first row of stone blocks. Block-laying is carried out using a band-saw to ensure precision and accuracy when creating doorways and windows.
Continuation of the laying of blocks with special attention paid to the accuracy of the horizontal and vertical lines.
General review of construction site and commencement of window apertures.
Continuation of the laying of blocks to a height of 1600mm
General review of the construction site on the morning of 27th December with the walls marked at 2400mm.
The first working day of 2014. In the last days of 2013, both the lintels and the beams of the first floor were mounted.
General review of the construction site in the morning of 9th January 2014. Pictures show the temporary flooring put in place and continued construction of the first floor walls.
January morning snow. Stone walls of the first floor are nearing completion. One row of blocks is prepared and left for installation of slabs.
General review of the building site on the morning of 16th January 2014. The walls of the first floor are ready for the installation of slabs.
Production of required works for the installation of items from JÄMERÄ (beams and cross pieces).
Work is continuing in the warm days of February. The house continues to grow! Work continues for the installation of items from JÄMERÄ (beams and cross pieces). The installation of boxes is nearing completion. Before the installation of covering plates, one row of blocks has been left aside. In the distance the driving range is visible.
Installation of boxes is completed. Preparation begins on the construction of the roof-unit.
Work begins on the roof-unit.
Installation of windows and roof-unit continues.
Frosty but sunny spring morning.
Work on the roof unit continues.
Work on the roof unit continues.
Insulation laid down, vapour barrier and roof cover.
Waterproofing of roof completed.
Decoration of facades begins.
Application of base coat for decorative plaster.
Preparation of walls under façade cladding board.
Partial decoration of wall façade.
Completion of façade on one side (plaster and board). Work begins on rafters.
Work on façade continues.
Work on façade continues.
Continuation of decorative work.
Completion of plasterwork on the façade. Work on the façade cladding board is underway.
Continuation of work on the façade cladding board.
Work on the façade is ongoing and nearing completion.
Completion of both plasterwork on the façade and cladding.
Installation of roofing underway.
Completion of wall base.
Completion of fencing around second-floor terrace.