GOLF VILLA

18.12.2013

Completion of the first row of stone blocks. Block-laying is carried out using a band-saw to ensure precision and accuracy when creating doorways and windows.

20.12.2013

Continuation of the laying of blocks with special attention paid to the accuracy of the horizontal and vertical lines.

23.12.2013

General review of construction site and commencement of window apertures.

25.12.2013

Continuation of the laying of blocks to a height of 1600mm

27.12.2013

General review of the construction site on the morning of 27th December with the walls marked at 2400mm.

07.01.2014

The first working day of 2014. In the last days of 2013, both the lintels and the beams of the first floor were mounted.

09.01.2014

General review of the construction site in the morning of 9th January 2014. Pictures show the temporary flooring put in place and continued construction of the first floor walls.

14.01.2014

January morning snow. Stone walls of the first floor are nearing completion. One row of blocks is prepared and left for installation of slabs.

16.01.2014

General review of the building site on the morning of 16th January 2014. The walls of the first floor are ready for the installation of slabs.

20.02.2014

Production of required works for the installation of items from JÄMERÄ (beams and cross pieces).

27.02.2014

Work is continuing in the warm days of February. The house continues to grow! Work continues for the installation of items from JÄMERÄ (beams and cross pieces). The installation of boxes is nearing completion. Before the installation of covering plates, one row of blocks has been left aside. In the distance the driving range is visible.

04.03.2014

Installation of boxes is completed. Preparation begins on the construction of the roof-unit.

11.03.2014

Work begins on the roof-unit.

13.03.2014

Installation of windows and roof-unit continues.

17.03.2014

Frosty but sunny spring morning.

01.04.2014

Work on the roof unit continues.

03.04.2014

Work on the roof unit continues.

18.04.2014

Insulation laid down, vapour barrier and roof cover.

21.04.2014

Waterproofing of roof completed.

08.05.2014

Decoration of facades begins.

13.05.2014

Application of base coat for decorative plaster.

15.05.2014

Preparation of walls under façade cladding board.

16.05.2014

Partial decoration of wall façade.

20.05.2014

Completion of façade on one side (plaster and board). Work begins on rafters.

23.05.2014

Work on façade continues.

23.05.2014

Work on façade continues.

27.05.2014

Continuation of decorative work.

03.06.2014

Completion of plasterwork on the façade. Work on the façade cladding board is underway.

06.06.2014

Continuation of work on the façade cladding board.

18.06.2014

Work on the façade is ongoing and nearing completion.

19.06.2014

Completion of both plasterwork on the façade and cladding.

04.07.2014

Installation of roofing underway.

10.07.2014

Completion of wall base.

19.07.2014

Completion of fencing around second-floor terrace.